2nd Niger Bridge: See The Upclose Images Of The Ongoing Construction - Read Progress Report – AutoReportNG
Connect with us

Roads & Construction

2nd Niger Bridge: See The Upclose Images Of The Ongoing Construction – Read Progress Report

Published

on

Second-Niger-Bridge
Spread the love

Some few days back, we did an update into the ongoing construction of the 2nd Niger Bridge. Even though there are still some doubting Thomases who still claimed and doubt the progress of the work despite all the images available to their disposal to verify.

The company handling the project, Julius Berger Nigeria Plc has released a progress report of the ongoing construction of the 2nd Niger Bridge. The new images released were more explicit, detailed and show the real progress with a date attached to the pictures so that no one will doubt the authenticity of the images and time.

The company said the project is expected to be completed by February 2022, adding that the scope of works includes the construction of 1.6km long bridge, 10.3km highway, Owerri interchange and a toll station.

These are the latest pictures of the work done on the Second Niger Bridge, November 2019 update as obtained by AutoReportNG. Pictures courtesy Julis Berger Nig PLC.

READ: Second Niger Bridge: See The Latest Development, New Look As Work Advances – PHOTOS

Earthworks CH 25+000 to 25+100 – Hydraulic dredging into alignment
Western approach –Casting station – Web and bottom reinforcement for Segment 1
Western Approach Axis 110 – 150 – Installation of lateral guide
Western Approach Axis 240 – Pier head completed
Niger Bridge Axis 260 – Pier table – Bottom part (North and South) completed
Eastern Approach – Axis 330 – Installation of wall reinforcement
Eastern Approach – Casting station – Installation of reinforcement for pile cap
Single Box Culvert CH 29+800 – Formwork and reinforcement
Soil Improvement CH 30+175 – Installation of GECs
Soil Improvement CH 31+750 – Laying of geotextile
Soil Improvement CH 32+100 LHS – Installation of PVD
Earthworks CH 33+200 – Working platform for GEC

To read the full report, click here to download the detailed report


Spread the love

AutoReportNG is your one-stop place for quality news on roads, cars, and anything pertaining to mobility. We keep track of all current news in road, rails, and aviation. We are known to true, factual and investigative news.

Trending

FAQ und Support-Chat helfen euch ebenso weiter wie die einfache Menüführung. casino spielen Auch das Feuer speiender berg (umgangssprachlich) Las vegas Bonus Guthaben unterliegt natürlich solchen Konditionen. https://vulkan-vegas.de Der Bonusbetrag ergibt sich” “mit jeder zeit aus deinem Gesamtwert der Einzahlungen kklk Tages geteilt durch Fünf. vom vulkan So sind sowohl Freispiele als auch kleinere Bonusguthaben für pass away nächste Einzahlung möglich. vulkan vegas