Roads & Construction

FG Announced Total Shutdown Of Third Mainland For Three Days

Published

on

Federal Government has announced a total shutdown of Third Mainland Bridge in Lagos for three days from midnight tomorrow to midnight on Sunday to carry out special repair works on the 11.8km platform.

Federal Controller of Works in Lagos, Mr Olukayode Popoola, said in a statement that the construction had reached a stage where there should not be any form of movement or vibration on the bridge for concrete casting, hence the closure.

“The first total closure of the section of the bridge between Adekunle and Adeniji Adele will be from midnight of Friday, 9th October 2020 to midnight of Sunday, 11th October 2020 to allow the contractor complete the first stage of casting works.

“The contractor, Messrs Borini Prono & Co. (Nig.) Ltd is nearing completion of works on the closed section of Third Mainland Bridge and requires the total closure of both bounds of the bridge between Adeniji Adele and Adekunle (i.e. in addition to the closed bound of the bridge, the other bound from Adekunle to Adeniji Adele will also be closed) to complete work.

“The total closure of this section of the bridge is to ensure that there is no vibration on the bridge during the casting in-place of the newly installed expansion joints. This is to allow for the setting of the special concrete, which allows the concrete to achieve its required compressive strength.

“Due to the number of expansion joints to be cast on the closed section of the bridge and the traffic situation in Lagos State, especially during the weekdays; the casting of the expansion joints will be in two stages to ensure that the total closure is only at the weekends when there is less traffic plying the route,’ ’he said.

The controller said that adequate traffic management officials would be deployed to man all the alternative routes to help with traffic flow and expressed regret at any inconvenience the closure might cause.

Popoola added that the second total closure of the section of the bridge between Adekunle and Adeniji Adele would be communicated at a later date.

Third Mainland Bridge in Lagos, which was going through a series of repairs, was partially shut on July 24 for another round of rehabilitation works.

The repair is expected to last for six months with the construction divided into two phases of three months on each carriageway, starting with the Oworonsoki bound carriageway.

Click to comment

Trending

Exit mobile version