Apapa-Oworonshoki Expressway Road Project Will Be Ready By November -FG – AutoReportNG
Connect with us

Roads & Construction

Apapa-Oworonshoki Expressway Road Project Will Be Ready By November -FG

Published

on

Spread the love

The Federal Controller of Work in Lagos, Mr Kayode Popoola, has reaffirmed the Federal Government’s commitment to delivering the Apapa/Oshodi/Ojota/Oworonshoki Expressway project on schedule.

L-R: Mr Kayode Ibrahim, Federal Ministry of Works (FMW) engineer, Mrs Musilimat Aloba, FMW engineer supervising Apapa-Oshodi-Ojota-Oworonshoki Expressway reconstruction project, Mr Kayode Popoola, Federal Controller of Works in Lagos and Mr Ashton Davies, Project Manager, Hitech during the inspection of ongoing Apapa-Oshodi-Ojota-Oworonshoki Expressway Reconstruction project on Wednesday in Lagos. [NAN]

It will be recalled that President Muhammadu Buhari flagged off the N73 billion project in November 2018 to address gridlock on the axis, promising to deliver it in two years.

During an inspection of the highway, on Wednesday, in Lagos, Popoola said that the road had achieved varied proportions of completion levels on different sections.

He explained that the progress was better to be presented in segments, but that a merger brought the entire projects to about 40 per cent completion level.

“On section one here, we have achieved about 22 per cent completion and on section three, it is about 55 per cent.

“On section four, we have achieved about 20 per cent completion,’’ he said.

On the completion date, the controller quoted the Minister, Mr Babatunde Fashola, as saying “it is still November this year’’.

While inspecting section one of the project, Popoola said “we are carrying out purification; which means, we removed the existing asphaltic concrete, add the stone base and now lay it’’.

He explained that several layers of construction went underneath, with up to eight inches thickness of concrete, to make the rigid pavement strong for durability.

The controller said that because of the huge vehicular and axle load on Apapa roads, the design was made to have iron rods as reinforcement to make the road stronger than normal asphaltic roads.

Apapa-Oshodi Expressway

He said that the project had created about 600 direct jobs and over 1,000 indirect jobs, thereby improving the livelihoods.

He further explained that the project, being handled by the Dangote Group, had reduced travel time because completed sections that had been opened to traffic and had eased congestion on the axis.

The controller also inspected section four, which is about 10.5 kilometres and spans from Anthony Village to Old Toll Gate.

According to him, the award of contract for section two is being processed.

“Section two, which spans from Beachland to Cele bus stop, is not part of this contract, but it is being processed and very soon, work will begin there.

“We are completing sections one, three and four in November 2020,’’ he restated.

While inspecting section four, Popoola said that the team had gone round Tin Can Island Port, Liverpool Road and various sections and subsections of the highway.

He said that skeletal work continued on the project during the COVID-19 lockdown, adding that, full capacity operations were still hampered.

According to him, this is because some staff were trapped in other states and could not return due to inter-state travel restrictions.

Apapa-Oshodi-Ojota Construction

“However, the workers resident in Lagos are coming to site.

“We have over 600 workers working here and it has improved the economy,’’ he said.

He appealed to Lagos residents to take ownership of the project and stop all forms of road abuses.

He decried dumping of refuse in drains of the ongoing project and others across the state while soliciting the support of residents on proper refuse disposal.

During an inspection of the 2.7 kilometres segment on section one B, Mr Ashton Davies, the Project Manager, Hitech subcontractors on the project, said that the technology used ensured continuity.

Davies explained that “with the concept of continued reinforcement pavement, there is no breakage and there is continuation of the concrete’’.

Construction Site Apapa Oshodi Ojota Expressway

He added that various completed sections could easily be linked.

Some road users who spoke to journalists expressed satisfaction with the speed of work on the project.

Mr Adelani Friday, a data analyst, called on the government to replicate rigid roads across the nation.

Also, Mr Gafar Olakunle, a truck driver that plies the Lagos-Ibadan Expressway, commended the quality of work being done.

Olakunle called on other private sector concerns to partner with the government on road construction as the Dangote Group has done.


Spread the love

AutoReportNG is your one-stop place for quality news on roads, cars, and anything pertaining to mobility. We keep track of all current news in road, rails, and aviation. We are known to true, factual and investigative news.

Trending

FAQ und Support-Chat helfen euch ebenso weiter wie die einfache Menüführung. casino spielen Auch das Feuer speiender berg (umgangssprachlich) Las vegas Bonus Guthaben unterliegt natürlich solchen Konditionen. https://vulkan-vegas.de Der Bonusbetrag ergibt sich” “mit jeder zeit aus deinem Gesamtwert der Einzahlungen kklk Tages geteilt durch Fünf. vom vulkan So sind sowohl Freispiele als auch kleinere Bonusguthaben für pass away nächste Einzahlung möglich. vulkan vegas