Lagos-Ibadan Railway To Kickstart In September With 16 Daily Trips – NRC

Published

on

Lagos-Ibadan Railway
Spread the love

The Nigerian Railway Corporation (NRC) is to commence skeletal operations on the Lagos-Ibadan Standard Guage Rail line from the middle of September with 16 trips daily.

Lagos-Ibadan Railway Site

The Managing Director of NRC, Mr Fidet Okhiria disclosed this on Saturday in Ibadan during an inspection tour of the project by the Ministers of Transportation, Mr Rotimi Amaechi and Information and Culture, Alhaji Lai Mohammed.

Okhiria said that since the track laying had been completed between Ebute-Metta Junction (EBJ) in Lagos and Ibadan with stations under construction, the operation would start between Yaba in Lagos and Ibadan.

“We will start by the middle of September from Yaba to Ibadan while the other construction finishing will continue.

“We already have 24 coaches and a set of DMUs (Diesel Multiple Units) made of eight coaches.

“With that, we intend to have 16 trips a day,” he said.

According to him, the corporation will not wait for all the stations to be ready before commencing operations so that Nigerians can start enjoying the dividends of the tracks and coaches that have arrived.

Ibadan Railway

NAN reports that the rail tracks on the 156km modern rail line have been completed from EBJ to Ibadan while the 10 major and minor stations are at various stages of completion.

The stations along the corridor are Apapa, EBJ, Agege, Agbado, Kajola, Papalanto, Abeokuta, Olodo, Omi-Adio and Ibadan. .

Speaking on the completion time for the project Amaechi said they were targeting January 2021 if the Covid-19 will not be a constraint to the workers.

“Before Covid-19, for every station, we have between 150 to 200 workers but now we have 10 to 20 workers on the sites.

“We have told them now to increase the number of workers and manage COVID very well.

“Covid-19 has come to stay but the government has to run.

“We have to deliver our promises to the people because that is why we are elected, so, let us hope that by January Ex year, the project will be ready, he said.

The minister admonished the Chinese contractor handling the project to speed up work on the construction for timely delivery.

Lagos Ibadan Railway


Spread the love

AutoReportNG is your one-stop place for quality news on roads, cars, and anything pertaining to mobility. We keep track of all current news in road, rails, and aviation. We are known to true, factual and investigative news.

Trending

FAQ und Support-Chat helfen euch ebenso weiter wie die einfache Menüführung. casino spielen Auch das Feuer speiender berg (umgangssprachlich) Las vegas Bonus Guthaben unterliegt natürlich solchen Konditionen. https://vulkan-vegas.de Der Bonusbetrag ergibt sich” “mit jeder zeit aus deinem Gesamtwert der Einzahlungen kklk Tages geteilt durch Fünf. vom vulkan So sind sowohl Freispiele als auch kleinere Bonusguthaben für pass away nächste Einzahlung möglich. vulkan vegas