Since the approval of this village, little or nothing was heard or seen in the media to fact check the progress of the railway compound. What many do not know is that the railway compound is part of the Itakpe-Ajaokuta-Warri Ore Rail Line.
The Agbor Railway village was on May 18th 2019 approved by the Federal Executive Council with the sum of 1.8billion naira for the reconstruction and rehabilitation of buildings of railway village in Agbor, Delta. The Railway Village which was burnt with this money will be rehabilitated and reconstructed just as the Railway yard and it will comprise of school, hospital and maintenance units.
According to a fact check done by AutoReportNG.com, our investigations revealed that the contract was contracted to Julius Berger Nigeria PLC.
The Railway Facilities form part of the Itakpe-Ajaokuta-Warri Ore Rail Line development, a standard gauge railway line initially meant to serve the steel-producing industry and later upgraded to a multipurpose railway line serving also the public transport. The works comprised of the completion of the railway maintenance depot and 20 Bridges over the railway line.
The railway maintenance depot is located close to Agbor village and is an essential part of the railway operation. There are 20 incomplete buildings at various construction stages. The infrastructure had to be brought in working condition. While some buildings only required roofing, finishing and interior, the majority had to be built from the foundations or even entirely. Most of the buildings were workshops and warehouses in different sizes but also the administration building, running control building and various minor structures had to be constructed or completed. In terms of infrastructure works, it was required to finish roads and drainages, power generation and distribution, water distribution and sewage collection. The initial design from the client had been adapted and improved to reflect the latest technologies at the time of completion.
The bridges for completion are located between the railway maintenance depot and Warri and were at different phases of completion. All the basic pre-cast concrete structures over the railway line were already erected and required construction of abutments, decking, embankments and roadworks for most of the bridges. One bridge needed to be upgraded by dualization of the initial bridge design. Due to the urbanization surrounding several bridges, the traditional embankment design had to be redesigned and replaced adapting the reinforced earth technology.
AutoReportNG brings to you update from the Agbor Railway Village and how work is faring from all angles.